2024 GO Referendum - Unpaved Streets

View all

Project Description:

In 2018, a study looked at all the unpaved streets in Durham. It found:

  • 179 unpaved streets totaling over 19 miles
  • Most of these streets are in residential areas, but some are for commercial use

In 2019, the City Council decided to pave all these unpaved roads within 10 years. With an annual budget of about $1.2 million, we've paved about 6 miles since then. There are about 13 miles of unpaved streets left, with 2.45 miles planned to be paved in 2024.

Bond Funding: $10,000,000

Project Timeline:

Paving will start in summer 2025 with a projected completion date sometime in 2029.